Proven Performance

A Remote WA Industrial Site Saved $350,000 with Rombus

A Remote WA Industrial Site Saved $350,000 with Rombus

Remote hardstand strength with less concrete, cost and downtime.

A Newman steel culvert and stormwater pipe manufacturer needed a durable hardstand for continuous heavy vehicle traffic, road trains and 16T forklifts. With remote concrete costs exceeding $850/m³, Rombus Fusion V2 was selected to reduce concrete use, speed up installation and minimise operational disruption.


Business: Leading steel culvert and stormwater pipe manufacturer
Industry: Industrial Manufacturing & Heavy Vehicle Infrastructure
Location: Newman, Western Australia
Project: 4,500m² Industrial Hardstand
Product: Rombus Fusion V2 Flexible Concrete Pavement System


The Challenge

The Newman facility required a durable hardstand surface capable of handling continuous heavy vehicle traffic and extreme loading conditions. The site needed a practical pavement solution that could be installed quickly, reduce project costs, and minimise disruption to ongoing operations.

Challenges Included

  • Remote project location where concrete costs exceeded $850 per cubic metre
  • Heavy-duty operational demands, including road trains and 16T forklifts
  • Requirement for a durable hardstand surface suitable for continuous industrial use
  • Need to reduce imported materials, earthworks and mobilisation requirements
  • Traditional concrete construction would require significantly more concrete
  • The client needed a faster installation method without compromising performance


The Solution

Rombus Industries installed 4,500m² of Rombus Fusion V2 across the Newman facility using the existing in-situ soils, which were trimmed to level with no imported fill required. This was a major advantage for a remote WA site where concrete costs exceeded $850 per cubic metre and minimising material transport, site preparation and downtime was critical. The modular pavement system was installed by a 7-person crew in just 9 days, including a peak pour of 1,250m² in a single day.

Why this solution worked for the project

  • Used the existing site soils, reducing the need for imported fill
  • Reduced concrete requirements compared to a traditional 150mm slab
  • Supported the facility's heavy-duty traffic, including road trains and 16T forklifts
  • Allowed the hardstand to be completed quickly with minimal operational disruption


The Result

The completed Rombus Fusion V2 installation delivered significant benefits across cost, construction time, sustainability and operational efficiency.

Major Cost Savings

  • Achieved approximately $350,000 in client-verified savings compared to a conventional concrete alternative.
  • Savings were achieved by reducing concrete volume, limiting imported material requirements and simplifying the construction process.

Reduced Concrete Use

  • Required only 207m³ of concrete.
  • A traditional 150mm slab would have required approximately 675m³ of concrete.
  • Delivered a total concrete reduction of 468m³.

Reduced Carbon Footprint

  • Avoided more than 140,000kg of CO₂ emissions through reduced concrete consumption.
  • Further environmental benefits were achieved by reducing imported materials, earthworks and transport requirements.

Sustainability Benefits

  • Used approximately 21,400kg of recycled plastic.
  • Rombus Fusion V2 is manufactured using 100% recycled Australian polypropylene.

Faster Install

  • The 4,500m² hardstand was installed in just 9 days.
  • Installed by a 7-person crew.
  • Achieved a peak pour of 1,250m² in a single day.
  • Helped reduce downtime and disruption to ongoing operations.


Newman, Western Australia Industrial Hardstand

"By reducing concrete volume, installation time and site preparation requirements, the Rombus Fusion V2 system provided a smarter, more economical hardstand solution for a remote heavy-duty industrial facility."


Thank you

United Ag recognises Rombus Industries for sharing this project and the proven results achieved at the Newman, WA facility.

This case study highlights how smarter pavement technology can help industrial operations reduce cost, concrete use, carbon emissions and construction time without compromising heavy-duty performance.

For more information about how the Rombus Flexible Concrete Pavement System can support your hardstand, pavement or industrial flooring project, visit www.unitedag.com.au/collections/rombus

Published June 2026

Contact Us today